When Should You Recalculate Process Behavior Chart Limits?
Recalculate the natural process limits when the chart shows a sustained shift, such as a run of 8, and the new level is expected to last. Calculate the new limits from the data after the shift. Don't recalculate after every new point, or real changes will widen the limits and disappear.
Key facts
- Recalculate after a sustained, explained shift, not on a schedule.
- Use data from after the change for the new limits.
- Wait for enough new points: provisional limits from 6 or more, firmer from about 20.
How Mostly Stable does it
The Mostly Stable app does this automatically for every metric. When it detects a sustained shift (a run of 8, 3 of 4 points near a limit, or 4 points in a row outside the limits), it starts a new calculation window at the start of that pattern, with provisional limits from its first 6 points, so the chart keeps reflecting how the process behaves now.
Updated 2026-11-08. Method: Shewhart's control chart as taught by Donald Wheeler in Understanding Variation.